Table 5.5.2: Hydroelectric Projects Under Operation in Bihar

Project No. Name of Project River / Canal Source District Installed Capacity (MW)
1.Son Western Link Canal HE Project, DehriSon CanalRohtas6.6 MW
2.Son Eastern Link Canal HE Project, BarunSon CanalAurangabad3.3 MW
3.Eastern Gandak Canal HE Project, ValmikinagarGandak CanalWest Champaran15.0 MW
4.Kosi Hydel Power Station, Kataiya, BirpurKosiSupaul20.0 MW
5.Agnoor Small Hydel ProjectSonArwal1.0 MW
6.Dhelabagh Small Hydel ProjectSonRohtas1.0 MW
7.Nasriganj Small Hydel ProjectSonRohtas1.0 MW
8.Triveni Link Canal HEPGandakWest Champaran3.0 MW
9.Jainagra Small Hydel ProjectSonRohtas1.0 MW
10.Shrikunda Small Hydel ProjectSonRohtas0.7 MW
11.Sebari Small Hydel ProjectSonRohtas1.0 MW
12.Belsar Small Hydel ProjectSonArwal1.0 MW
13.Arwal Small Hydel ProjectSonArwal0.5 MW
Total Operational Capacity 54.3 MW
⭐ Key Points
  • 1., Installed Capacity (MW): 6.6 MW
  • 2., Installed Capacity (MW): 3.3 MW
  • 3., Installed Capacity (MW): 15.0 MW
  • 4., Installed Capacity (MW): 20.0 MW
  • 5., Installed Capacity (MW): 1.0 MW
  • 6., Installed Capacity (MW): 1.0 MW
📌 One-line Q&A
  • 1., Installed Capacity (MW): 6.6 MW
  • 2., Installed Capacity (MW): 3.3 MW
  • 3., Installed Capacity (MW): 15.0 MW
  • 4., Installed Capacity (MW): 20.0 MW
  • 5., Installed Capacity (MW): 1.0 MW
  • 6., Installed Capacity (MW): 1.0 MW
Questions 1 MCQs

Answer this question, then use Next.

Which operational hydroelectric station in Bihar has the highest installed capacity according to Table 5.5.2?

Kosi Hydel Station at Kataiya (Supaul) has the highest capacity at 20.0 MW.
Question 1 of 1

Write your answer, then submit to see the correct answer.

1., Installed Capacity (MW): ______

6.6 MW

2., Installed Capacity (MW): ______

3.3 MW

3., Installed Capacity (MW): ______

15.0 MW

4., Installed Capacity (MW): ______

20.0 MW

5., Installed Capacity (MW): ______

1.0 MW

6., Installed Capacity (MW): ______

1.0 MW